Hard Rock Construction, LLC has reached 80 percent completion on the $2.7M Lakeview North Group A Project. Barring weather delays, the job is slated to be complete by summer 2018. In the last 30 days, crews have finished concrete pours throughout areas of Bragg and Memphis Streets.
The scope of work varies block by block but will include the following:
- Patch Mill / Overlay: Repaving the asphalt roadway from curb to curb and repairing damaged sidewalks;
- Patch Concrete: Removing damaged portions of the concrete roadway and replacing it with new smooth concrete pavement;
- Incidental Road Repairs: Removing damaged portions of the asphalt roadway and replacing it with new smooth pavement; and
- Non-Paving Incidentals: Repairing damaged sidewalks, driveway aprons and curbs within the public right-of-way.
For more information about work on your block and other upcoming projects, please visit roadwork.nola.gov or call 504.658.ROAD (7623).